What Happens If Your Condo Fails Its Milestone Inspection?

A Phase 1 finding of substantial structural deterioration starts a defined process under Florida Statute 553.899: Phase 2, a sealed report, and a repair-start deadline. Here is what each step means for your board.
Concrete column with severe spalling and exposed, corroded reinforcing steel found during a condominium inspection

A Phase 1 milestone inspection does not issue a pass/fail grade like a test. If the inspector finds no signs of substantial structural deterioration, Phase 2 is not required. If substantial structural deterioration is identified, Florida Statute 553.899 requires a Phase 2 inspection, a sealed Phase 2 report, and, once that report reaches the local building department, a deadline to schedule or commence repairs, which must start within 365 days. In everyday language, “fail” usually means that Phase 1 finding, not an automatic order to vacate. If your board already has a Phase 1 report, call 1-800-903-8805.

New to milestone inspections? Start with our SB 4-D milestone inspection overview for who the law applies to and when the first inspection is due.

What “substantial structural deterioration” actually means

Section 553.899(2)(b), Florida Statutes, defines substantial structural deterioration as substantial structural distress or substantial structural weakness that negatively affects a building’s general structural condition and integrity.

In plain terms, it is a problem with the structure itself, not with its finishes. The definition does not include surface imperfections such as cracks, distortion, sagging, deflections, misalignment, signs of leakage, or peeling of finishes, unless the licensed engineer or architect performing the Phase 1 or Phase 2 inspection determines that those surface imperfections are a sign of substantial structural deterioration. That decision belongs to the inspector, so a board should not dismiss visible cracking on its own.

Unsafe or dangerous conditions are a separate finding

Every milestone report must also state whether unsafe or dangerous conditions, as those terms are defined in the Florida Building Code, were observed (s. 553.899(8)(d)). That is not the same as substantial structural deterioration. If your report flags unsafe or dangerous conditions, contact your local building official and our engineering team right away.

What happens after Phase 1 finds substantial structural deterioration

  1. Phase 2 is required (s. 553.899(7)(b)). Phase 2 may include destructive or nondestructive testing at the inspector’s direction. It may be as extensive or as limited as necessary to fully assess areas of structural distress, confirm that the building is structurally sound and safe for its intended use, and recommend a program for fully assessing and repairing distressed and damaged portions. Testing locations should favor the least disruptive and most easily repairable spots that are still representative of the structure.
  2. Phase 2 progress report. Within 180 days after the Phase 1 inspection report is submitted, the architect or engineer performing Phase 2 must submit a progress report to the local enforcement agency with a timeline for completing the Phase 2 inspection.
  3. Sealed Phase 2 report and summary. When Phase 2 is complete, a sealed copy of the report and a separate summary of material findings and recommendations go to the association, to any other owner of a portion of the building not in condominium or cooperative ownership, and to the building official (s. 553.899(8)). At a minimum, the report covers the inspector’s seal and signature, the manner and type of inspection, any substantial structural deterioration and recommended repairs, whether unsafe or dangerous conditions were observed, remedial or preventive repairs for damaged items that are not substantial structural deterioration, and items that need further inspection.
  4. Unit-owner notice within 45 days. Within 45 days after receiving the applicable inspection report, the association must distribute the inspector-prepared summary to each unit owner (by mail or personal delivery, and electronically to owners who consented), post the summary in a conspicuous place on the property, and publish the full report and summary on the association website if the association is required to have one (s. 553.899(9)). This applies regardless of the findings.

For who needs a milestone inspection in the first place (residential condominium and cooperative buildings three habitable stories or more, first inspection at 30 years, or 25 years if the local agency requires it, then every 10 years), see our SB 4-D milestone inspection page.

The 365-day repair-start deadline

Section 553.899(11) requires each county or city to adopt an ordinance requiring the association, and any other owner subject to the law, to schedule or commence repairs for substantial structural deterioration within a set timeframe after the local enforcement agency receives the Phase 2 inspection report. Those repairs must be commenced within 365 days after the agency receives that report.

  • The deadline is to start, not to finish. The statute’s clock is about scheduling or commencing repairs. If the work will take longer than a year, the association still needs proof that repairs were scheduled or started on time.
  • Your local ordinance may be shorter. If your city or county requires an earlier start, follow the local rule.
  • Missing it triggers a safety review. If the owner does not submit proof to the local enforcement agency that repairs have been scheduled or have commenced within the required timeframe, the agency must review and determine whether the building is unsafe for human occupancy.
  • Plan for permits. Structural, concrete, and electrical repairs generally need building permits, so repair design and permit drawings should start well before the deadline.

Many associations also have Structural Integrity Reserve Study duties that affect how repairs are planned and funded. See our SIRS page.

What the board should do in the first 30 days

  1. Read the Phase 1 report and the inspector-prepared summary carefully. Note whether the finding is substantial structural deterioration, unsafe or dangerous conditions, or recommended preventive repairs only.
  2. Calendar the 180-day Phase 2 progress-report date (measured from submittal of the Phase 1 report) and, once Phase 2 is in, the repair-start deadline (measured from the local agency’s receipt of the Phase 2 report, or earlier if your local ordinance says so).
  3. Complete the 45-day unit-owner distribution, posting, and website publication.
  4. Engage a team for Phase 2 testing and for repair design, so permit drawings are underway before the 365-day clock becomes an emergency.
  5. Ask your local building department what proof of “scheduled or commenced” it will accept, such as a signed contract, an issued permit, or started work.
  6. Call 1-800-903-8805 if your board wants our engineering team and construction team on the Phase 2 and repair path.

This page is general information about Florida’s milestone inspection law, not legal advice. Confirm deadlines with your local building department and your association’s counsel.

Already have a Phase 1 report?

Send it to us. Our engineering team will review the findings and recommend a Phase 2 and repair-design scope, so your board can plan ahead of the 365-day repair-start deadline. Call 1-800-903-8805.

Talk with our engineering team
Concrete balcony and walkway repairs underway along a two-story apartment building

How our engineering team and construction team help after a Phase 1 finding

1. Review the Phase 1 report

We go through the Phase 1 report and summary with your board, separate substantial structural deterioration from unsafe conditions and preventive items, and calendar the statutory and local deadlines.
Exterior and balconies of a mid-rise condominium building inspected as part of a milestone inspection

2. Phase 2 inspection and testing

Our engineering team plans and performs the Phase 2 inspection, including destructive or nondestructive testing where needed, and prepares the progress report and the sealed Phase 2 report.
Inspection opening cut in a walkway ceiling to expose the structural framing above

3. Repair design and permits

We design the repairs the report requires and prepare permit documents, so the board can show that repairs were scheduled or commenced on time.
Tape measure recording the depth of a deteriorated concrete slab edge for repair design

4. Construction and closeout

Our construction team performs the permitted repairs and coordinates the inspections and documentation needed to close out the work with the building department.
Construction crew member preparing a second-floor concrete walkway for repair
A note on inspection and repair bids. Souffront offers both inspection and repair services. Section 553.899(12), Florida Statutes, requires written disclosure when a design professional or a licensed contractor bids on maintenance, repair, or replacement recommended by a milestone inspection and has an interest in the firm that provided the inspection, or is a relative of someone who does. Any repair bid we submit for work recommended by a milestone inspection we performed will include the written disclosure the statute requires.

Failed milestone inspection: frequently asked questions

What happens if my condo fails its milestone inspection?

Florida’s milestone law does not use a pass/fail grade. If Phase 1 finds no substantial structural deterioration, Phase 2 is not required. If Phase 1 does identify substantial structural deterioration, a Phase 2 inspection is required, a sealed Phase 2 report must be submitted, and repairs for that deterioration must be scheduled or commenced within 365 days after the local building department receives the Phase 2 report, or sooner if a local ordinance says so.

What does “substantial structural deterioration” mean?

Under Florida Statute 553.899, it means substantial structural distress or substantial structural weakness that negatively affects the building’s general structural condition and integrity. Surface issues such as cracks, sagging, leakage stains, or peeling finishes are not automatically included, unless the inspector determines they are a sign of that deterioration.

Is Phase 2 required if Phase 1 finds only cracks or leaks?

Only if the inspector determines those conditions are a sign of substantial structural deterioration, or otherwise identifies substantial structural deterioration during the Phase 1 visual examination. If Phase 1 finds no signs of substantial structural deterioration, Phase 2 is not required. The report may still recommend preventive or remedial repairs for damaged items that are not substantial structural deterioration.

How long do we have to start milestone inspection repairs?

Repairs for substantial structural deterioration identified in a Phase 2 report must be commenced within 365 days after the local enforcement agency receives that Phase 2 report. A city or county ordinance may require the association to schedule or start the work sooner. The statute requires the work to start (or be scheduled and then started in that window); it does not require the project to be finished in 365 days.

What if we do not start the repairs in time?

If the owner does not submit proof to the local enforcement agency that repairs have been scheduled or have commenced within the required time, the agency must review the building and determine whether it is unsafe for human occupancy.

When is the Phase 2 progress report due?

Within 180 days after the Phase 1 inspection report is submitted, the architect or engineer performing the Phase 2 inspection must submit a Phase 2 progress report to the local enforcement agency with a timeline for completing Phase 2.

Do we have to share the report with unit owners even if the findings are serious?

Yes. Within 45 days after receiving the inspection report, the association must send the inspector-prepared summary to every unit owner, post it on the property, and publish the full report and summary on the association website if the association is required to have a website. That duty applies regardless of the findings.

Does a Phase 1 finding mean residents have to leave?

Not by itself. A finding of substantial structural deterioration triggers Phase 2 and, after the Phase 2 report, a repair-start deadline. A separate finding of unsafe or dangerous conditions, as defined in the Florida Building Code, is more serious and should be raised with the local building official immediately. Vacate or occupancy decisions are made under the building code and local enforcement, not by the everyday word “fail.”

Is a milestone inspection the same as Miami-Dade recertification or Broward BSIP?

No. The milestone inspection is a statewide structural inspection law for residential condominium and cooperative buildings that are three habitable stories or more. Miami-Dade recertification and Broward’s Building Safety Inspection Program are local programs that also include electrical inspections and have different deadlines. In Broward, official BORA policy states that a completed Building Safety Inspection serves as compliance for milestone Phase 1 and Phase 2; confirm filing details with your city. If your issue is a missed local filing deadline instead, see our violation and missed-deadline page.

Official sources

Have a Phase 1 finding?

If your Phase 1 report identified substantial structural deterioration, or you need Phase 2 and a repair plan before the 365-day clock runs, call 1-800-903-8805 or contact our engineering team.

Send your Phase 1 reportCall 1-800-903-8805

Our Inspection Team

John Souffront

President
Civil Engineer Major

Miguel C.

Director of Inspections
Civil Engineer Major

Abel G.

Lead Inspector II
Civil Engineer Major

Ricardo B EIT

Lead Inspector I
Civil Engineer Major
Meet the entire team that helps clients navigate inspections, repairs, and recertification with confidence.
Explore Our Team Page

Client Reviews

Souffront Construction went above and beyond to ensure that I recieved the most professionañ service. They assisted me with a certified assessment to submit to the condo board for approval of upgrades to my unit. Communicating with them was easy and timely. I would hire them again.

I have been working with Souffront Engineering for years now and the experience has always been professional, and timely.

Great service!

I have worked with Souffront Construction for about a year now. I highly recommend their services if you’re looking for a contractor that is reliable, knowledgeable, and passionate about what they do.

I cannot begin to say enough great things about Souffront Construction & Engineering.They are professional, attentive, efficient and very professional. I highly recommend Souffront Construction & Engineering.

Souffront Construction went above and beyond to ensure that I recieved the most professionañ service. They assisted me with a certified assessment to submit to the condo board for approval of upgrades to my unit. Communicating with them was easy and timely. I would hire them again.

I highly recommend this company for their exceptional service and professionalism. They demonstrated a strong commitment to quality and attention to detail throughout the entire process. Communication was clear, timely, and consistent both during and after the project. They successfully provided us with building.

Very diligent, quick and responsive service. Accurate and very reasonable. It's great to work with professionals with experience.

Great team , we used this Engineering Company for our building's 50-year recertification. The initial inspection was performed professionally , very much attention to all the details , and their reinspection was beyond . They stand behind their work . They are prompt and efficient . I extremely recommend this Company
Hide

I have worked with Souffront Construction for about a year now. I highly recommend their services if you’re looking for a contractor that is reliable, knowledgeable, and passionate about what they do.

Kudos to John and his team for the amazing work they did at our property. The team is very professional and they know what they are talking about. Highly recommended.

Professional, knowledgeable & just a great team to work with. A++ services.

Excellent Experience with Souffont Construction & Engineering!!!! The whole team was very knowledgeable and supportive and led me step by step through the process of a 40 year certification on a commercial building. They are very fast and responsive and were able to assist my colleague with obtaining a proposal on a large construction project aswell in less than a week!!!!

Souffront Construction went above and beyond to ensure that I recieved the most professionañ service. They assisted me with a certified assessment to submit to the condo board for approval of upgrades to my unit. Communicating with them was easy and timely. I would hire them again.

Excelent service

I'm a property manager of about 200 units. I've worked with Souffront Constructions for almost two years. They are very professional, cost effective and time efficient. I strongly recommend them.

John provided details and reviewed our home we were planning to purchased. Its was great to working with him.

Souffront Construction & Engineer Great service & they responded quickly to any concerns to there Service and Answered all my questions promptly by the way John was Great customer service !”

Amazing work ethic. Working with Jhon was an absolute pleasure to work with.

Our Condo Association has hired Souffront Engineering and Construction to do repairs to our buildings on several occasions. The work is always done in a thorough and professional manner and at a competitive price.

Souffront Construction & Engineering can be relied on to provide a professional and thorough service. Our condo association hired John Souffrant and his team to inspect our buildings for concrete work and water intrusion. We are pleased with the quality workmanship and professionalism of the team. We will reach out to Souffrant Construction for future needs.

Great Service. Very professional and honest.

Very professional. John is excellent at what he does.

Souffront Construction went above and beyond to ensure that I recieved the most professionañ service. They assisted me with a certified assessment to submit to the condo board for approval of upgrades to my unit. Communicating with them was easy and timely. I would hire them again.

Souffront Contruction team... Can't be better. Facts: John solved my doubts on some cracks on the garage floor over the phone first time I called him, not even charging me any money. Second time I called they came on a 24 hour turnover to check if a wall was load bearing, Guillermo came, another excellent person. This company is Honest and Professional, that is what I was looking for. Thank you.

Had a leaky pipe emergency. Souffrant was responsive, communicative and did careful work in exposing the pipe with minimal disruption. When the pipe was repaired they restored everything beautifully. They are skilled they are caring. I trust them with my home.

I got my job done from Souffront Construction. I was so happy with the quality of service that I received.

John and his crew were awesome. 40 yr certification inspection was done and they accommodated us within the time we needed done. Very responsive every time you contact them. Definitely recommend.

We hired Suffront construction for 40 year certification in Miami Fl. We are very happy with their prompt services & staff. we highly recommend them. Thank you John.

It’s a real pleasure to work with Souffront, the experience has been according to expectations, professionalism and quality through all the process. There is no doubt that we have planned to work in future projects together. Thanks for the amazing job performed and for the opportunity to work with you.

Our Completed Projects

OPKO Glass Building
Office Building
Biscayne Blvd
250,000
Recertification Repairs
view property
Warehouse Complex
Warehouse
Ft. Lauderdale
1,000,000
SIRS, Building Safety Inspection
view property
The Commodore
Residential Apartment Complex
Little Havana
15,000
Building Recertification
view property
Synagogue & House of Worship
Public Assembly
North Miami
8000 2 ft
Building Recertification
view property
Dadeland Marriot
High Rise
South Miami
100,000+
Building Recertification , Design and Repairs
view property
Palm Beach Shores Resort
Hotels & Resorts
Riviera Beach
500,000+
Milestone Inspection
view property

Contact us

Thank you! Your submission has been received!
Oops! Something went wrong while submitting the form.