How our engineering team and construction team close the file
1. Notice and case review

2. Inspection or report review

3. Report, extension, or occupancy letter

4. Repair design, permits, and construction

For the full program, including exemptions and report requirements, see our Broward Building Safety Inspection (BSIP) page. Source: BORA Policy #05-05.
A missed recertification or BSIP filing deadline is a local program-compliance problem. A milestone Phase 1 finding of “substantial structural deterioration” is a different, statewide process under s. 553.899, Florida Statutes: Phase 2, then repairs scheduled or commenced within 365 days after the local agency receives the Phase 2 report. See our SB 4-D milestone inspection page and what happens if your condo fails its milestone inspection.

The letter itself, with its date. Go by the letter, not by the old “40-year” nickname.

The property address and the folio or case number on the notice.

Any earlier structural or electrical recertification or Building Safety Inspection reports.

Open permits, repair records, and any letters from the county, the city, or the Unsafe Structures Section.




Miami-Dade’s official recertification portal states that if the owner does not obtain recertification in the required time, the property is referred to the Unsafe Structures Section and an enforcement case is opened. That section can post the building unsafe, issue a Notice of Violation, refer the case to the Unsafe Structures Board, set repair or vacate timelines, and collect enforcement costs. Call the number on your notice, and get the required structural and electrical report or a valid extension request moving immediately.
It depends on the county. In Miami-Dade, the recertification report is due within 90 days of the Notice of Required Inspection. In Broward, the Building Safety Inspection report is due within 180 days of the notice. Do not apply one county’s clock to the other.
In Miami-Dade, the Building Official may grant an extension of not more than 60 days to submit the recertification report or to obtain necessary permits, if a written request from an engineer or architect includes a signed and sealed statement that the building may remain occupied. In Broward, the Building Official may grant an extension of not more than 60 days to submit the BSIP report, and a separate short extension may be available to obtain repair permits. Extensions are not automatic.
Yes. The program names have changed (Miami-Dade recertification is now generally a 30-year / 25-year coastal cycle, and Broward BSIP starts at 25 years), but a missed filing can still be an open enforcement or unsafe-structures case. Check the Miami-Dade recertification portal or your Broward city building department for the current case status.
Under Section 8-11(f), the owner has 150 days from the date of the Notice of Required Inspection to finish repairs that do not need permits and to obtain any necessary permits. Permitted work then follows the active permit timeline. A letter stating the building may stay occupied during repairs is valid for no more than 180 days and must be renewed if work is still underway.
Unless the Building Official sets a different timeframe, you have 180 days from the date of the Building Safety Inspection report to complete the required structural and electrical repairs, with permits as required.
Not automatically. Those are possible later outcomes in an unsafe-structures or code-enforcement case if required inspections or repairs are not completed. The official Miami-Dade process includes notice, a case, possible posting, Board review, and orders to repair or vacate. The immediate need is to open a path back to compliance with a current report, any required occupancy letter, and a permitted repair plan.
In Miami-Dade, Section 8-11(f) allows the Building Official to order electrical utilities disconnected, in defined circumstances, if the recertification report was not timely filed and that failure creates uncertainty about safe occupancy. The Official must first give certified-mail and posted notice. A signed and sealed statement that the building may remain occupied is one of the listed ways to stop a disconnection. Take any “intent to disconnect” letter seriously and respond immediately.
For Miami-Dade recertification submittals, the county lists 786-315-2373 and RER-Recertification@miamidade.gov. For unsafe-structures cases, the recertification portal lists 786-315-2424. In Broward, call the city building department named on your notice. For help with the inspection, filing, and repairs, call Souffront at 1-800-903-8805.